YS Jagan Questions Rs.15,317 Crore Amaravati Project, Flags Rs.29,340 Per Sq Ft Cost

YS Jagan Questions Rs.15,317 Crore Amaravati Project, Flags Rs.29,340 Per Sq Ft Cost

Pinjari Chand
November 29, 2026

YSR Congress Party president and former Andhra Pradesh Chief Minister YS Jagan Mohan Reddy has questioned the steep escalation in the estimated cost of government buildings in Amaravati, alleging that the Chandrababu Naidu-led coalition government is spending an unusually high amount of public money on the capital city's construction projects.

Jagan questioned how the government could justify an expenditure of Rs.29,340 per square foot for government buildings, alleging that construction costs were being inflated in the name of international standards.

According to Jagan, the estimated cost of constructing the new Secretariat buildings stood at Rs.2,271 crore in 2018. After the coalition government assumed office in 2024, it cancelled the existing tenders and subsequently increased the project cost. In April 2025, the same companies were reportedly awarded the same works, but the contract value was raised to Rs.4,689 crore, he alleged.

Jagan claimed that the estimates had been revised again, taking the construction value of the same works to Rs.6,641 crore. An additional Rs.4,830 crore was being spent on glass installations, air-conditioning systems and other related facilities, he said.

As a result, the expenditure on five government buildings, covering a total built-up area of 52.20 lakh square feet, would reach Rs.15,317 crore. This translates to approximately Rs.29,340 per square foot, he pointed out.

Questioning the justification for such high costs, Jagan said the government was already providing concessions, including free sand, electricity charge benefits and exemptions from seigniorage and non-agricultural conversion charges.

He further argued that even premium buildings with five-star facilities in metropolitan cities such as Bengaluru, Hyderabad and Chennai could be constructed for less than Rs.5,000 per square foot.

"Is the government building international-standard structures or engaging in international-standard corruption?" Jagan questioned, targeting the Chandrababu Naidu government.

He alleged that the administration was placing an additional debt burden on the public while awarding expensive contracts to its preferred companies. Jagan accused the coalition government of misusing public funds in the name of Amaravati's development and demanded accountability over the escalating construction expenditure.