Pinarayi Vijayan Seeks Judicial Probe Into Kerala's VEH Global Power Deal

Pinarayi Vijayan Seeks Judicial Probe Into Kerala's VEH Global Power Deal

Saikiran Y
November 22, 2026

Leader of the Opposition in the Keralam Assembly Pinarayi Vijayan on Friday demanded a judicial probe into the state's 200 MW power purchase agreement with VEH Global, alleging irregularities in the procurement process, inflated electricity costs and the absence of a compelling need for the purchase. The demand comes amid mounting scrutiny from the Kerala State Electricity Regulatory Commission (KSERC), which has raised 15 questions concerning the agreement, including pricing, tender procedures, supplier eligibility and delayed regulatory approval.

Vijayan said Chief Minister V D Satheesan's defence of the agreement in Delhi had raised further doubts. Citing the KSERC's October 29 order in Petition No. 42/2026, he said 19 bids were received in a tender opened on September 10. Published on the DEEP portal on August 20, the tender covered night-time supply from October to May and peak-hour requirements from March to May. Six companies, including PTC India, RPG Power Trading, Tata Power Trading, Manikaran Power, Jindal Power and Shree Cement, participated, with all qualifying for financial bidding.

He questioned why the VEH Global agreement was signed on September 23, two days before another tender for October peak-hour electricity was opened. Vijayan alleged that the September 14 tender was intended to justify an already finalised agreement. He maintained that KSEB had secured 1,088 MW for October peak hours through three agreements covering 788 MW and a 300 MW power-swap arrangement.

The regulatory commission subsequently raised 15 queries, seeking details about the electricity source, supplier eligibility, trading margins, competitive bidding and the absence of prior approval. It also questioned why retrospective approval was sought nearly one-and-a-half months after procurement.

KSEB reportedly informed the commission that transmission charges of Rs 1.55 per unit increased the agreed Rs 11 tariff to Rs 12.55 per unit. Reports also indicated that 59.6 lakh units cost approximately Rs 7.48 crore, including around Rs 92 lakh in transmission charges. Another report put the payment at Rs 7.37 crore for an average supply of just 36.02 MW against the contracted 200 MW. Satheesan, however, maintained that payment was below Rs 5 crore.

The controversy also involves KSEB's separate purchase of around 900 MW from Himachal Pradesh at Rs 14.50 per unit, costing approximately Rs 282 crore during October. Reports indicated that Keralam had around 4,700 MW available that month, even without supplies from VEH Global and Himachal Pradesh. However, KSEB cited weak monsoon inflows, rising demand and anticipated peak-hour deficits of 1,200–1,500 MW in March and April 2027.

Satheesan rejected allegations of a Rs 496-crore scam and Rs 250-crore government loss, saying September tenders received no responses due to electricity shortages. He justified the Rs 11 tariff by citing prices of Rs 38 and Rs 41.50 per unit in Tamil Nadu and an NTPC offer of Rs 30.

Vijayan also raised concerns over alleged SEBI and Central Electricity Regulatory Commission proceedings involving VEH Global's parent company, INOXGFL. He demanded disclosure of documents relating to the GNA, VEH Global and Himachal Pradesh agreements, besides a judicial investigation.