Let's talk: editor@tmv.in
Nepal Gets India's Nod to Import 350 MW of Power as Winter Shortage Looms

Nepal Gets India's Nod to Import 350 MW of Power as Winter Shortage Looms

Bavana Guntha
November 19, 2026

Nepal has received approval to import up to 350 MW of electricity from India this winter as declining hydropower generation and flood damage to several projects threaten domestic supplies.

The Central Electricity Authority (CEA) under India's Ministry of Power has authorised the Nepal Electricity Authority (NEA) to purchase electricity at competitive rates through the Indian Energy Exchange (IEX) for up to 17 hours a day. The approval is valid from November 17, 2026, to July 31, 2027.

Of the approved capacity, Nepal can import 300 MW through the Kataiya-Kushaha, Ramnagar-Surajpura and Raxaul-Parwanipur transmission lines. The remaining 50 MW can be sourced through the New Nautanwa-Mainahiya transmission line.

NEA Managing Director Dirghayu Kumar Shrestha said the approval would help bridge the gap between domestic electricity generation and demand.

Nepal's winter power requirement is expected to rise considerably. During the peak period between mid-January and mid-March, the country may need continuous imports of 450-500 MW, with demand reaching 800-900 MW during peak hours. The newly approved 350 MW is part of its broader import arrangements.

Nepal's dependence on run-of-the-river hydropower makes electricity generation seasonal. Higher river flows during the monsoon allow it to generate surplus power for export, mainly to India, while falling water levels reduce production during winter.

Despite these seasonal imports, Nepal remains a net electricity exporter. In 2025-26, it imported power worth NPR 10.55 billion, while exports to India and Bangladesh generated NPR 29.32 billion, resulting in a trade surplus of approximately NPR 18.76 billion.

This winter, the situation has been aggravated by the August Rasuwa-Bhotekoshi floods, which damaged several hydropower projects. Plants with a combined installed capacity of 431 MW remain disconnected from the national grid.

Domestic generation is expected to recover from mid-April 2027 as river levels rise, potentially reducing imports and allowing Nepal to resume larger electricity exports.

Nepal Gets India's Nod to Import 350 MW of Power as Winter Shortage Looms - The Morning Voice