India's First Bullet Train: 2027 Launch Set, Project Cost Soars 108% to ₹2 Lakh Crore
India's First Bullet Train: 2027 Launch Set, Project Cost Soars 108% to ₹2 Lakh Crore

India's First Bullet Train: 2027 Launch Set, Project Cost Soars 108% to ₹2 Lakh Crore

Bavana Guntha
November 22, 2026

India's first bullet train project, originally targeted for completion in 2023, is now expected to begin operations on its first section in the last quarter of 2027, nearly a decade after construction was formally launched. The 508-km Mumbai–Ahmedabad High-Speed Rail corridor, initially estimated to cost ₹97,636 crore, has seen its projected cost rise to ₹2,02,797 crore.

The project was first explored through India-Japan discussions during 2009-2012. A feasibility study began in December 2013 and was completed in July 2015, proposing a 508-km corridor with 12 stations, a design speed of 350 kmph and a 2023 completion target.

The Union Cabinet approved the project in December 2015, with the sanctioned cost subsequently fixed at approximately ₹1.08 lakh crore. The National High Speed Rail Corporation Limited (NHSRCL) was established in 2016. Prime Minister Narendra Modi and then Japanese Prime Minister Shinzo Abe laid its foundation stone on September 14, 2017.

Construction faced major delays, particularly in Maharashtra, due to land acquisition and pending state permissions. The COVID-19 pandemic further disrupted construction and procurement. Railway Minister Ashwini Vaishnaw said these issues delayed the project by nearly four years, with full-scale construction beginning in 2021. The government subsequently reported completion of land acquisition.

The revised estimate of ₹2,02,797 crore represents an approximately 108 per cent increase over the original ₹97,636-crore estimate, more than doubling the projected cost. Major additional expenses include ₹29,330 crore in taxes and cess, ₹19,084 crore due to inflation and price escalation, ₹16,695 crore for land acquisition and rehabilitation, and ₹16,500 crore for indigenous trains and signalling.

Actual expenditure reached ₹92,761 crore by March 2026, according to an RTI disclosure. The revised estimate was reported as awaiting formal sanction.

Japan's JICA is financing 81 per cent of the original sanctioned cost through a loan carrying 0.1 per cent interest, a 50-year repayment period and a 15-year moratorium.

Vaishnaw announced on November 20 that the first service would operate between Surat and Vapi in October–December 2027, with the remaining corridor opening in phases. By September 2026, 456 km of pier work and 371 km of viaduct construction had been completed. The project also includes a 21-km Maharashtra tunnel, including seven km beneath Thane Creek.

Meanwhile, ICF and BEML are manufacturing the indigenous B28 trainset, designed for 280 kmph. Its first body frame is complete, with track trials expected by mid-2027. The corridor is designed for 350 kmph, with a planned operating speed of 320 kmph.

India's First Bullet Train: 2027 Launch Set, Project Cost Soars 108% to ₹2 Lakh Crore - The Morning Voice